
Electrical is run to the house and should be powered on by July 2 with lights.

Front Door with hardware.

Drive-way formed and ready for concrete. Concrete will be poured on July 2.

Patio formed and ready for concrete.

Forgot to mention - we only got one broken window from the rock layers. This will be replaced shortly.

AC vents were installed today in preparation to turn AC on before weeks end. Yeah...no more cleaning in the HOT Texas heat anymore.

Dryer vent installed.

Door hardware is all on.

Master Bath shower - detailed tile work in progress.


Microwave and vent hood installed.

More hardware

Dalton's Bath tile complete.

Dalton's Bath tile complete.

Dalton's Bath

Guest Bath tile work complete - waiting for tile on floor.
No comments:
Post a Comment